Mitigation activities completed in Bad Camberg

Bad Camberg/Trier. In 2017, four Enercon E-115 turbines were successfully installed in Bad Camberg, Hessen. Shortly after realization, the windfarm was sold to the CEE group, a Hamburg-based renewable asset manager. All replacement and mitigation activities are completed in time. Although the last two years of drought, the reforestation should be conducted in time.

Now the reforestation work is completed, we hope all the new bushes and trees will grow successfully. By completing the mitigation work, all conditions with regard to the permit are taken care off.

However, this only applies to the four existing WTGs, as six WTGs were originally planned by DunoAir Windpark Planung. We are still waiting for a permit for the last two wind turbines at this excellent site.