Substation Mastershausen
Project description
The Mastershausen substation was built to relieve the ever-tightening medium-voltage grid (20 kV) and to feed electricity directly into the high-voltage grid (110 kV).
Connected feeders:
Windfarm Mastershausen I (14 MW)
Solarpark Mastershausen (3 MW)
Windfarm Mastershausen II (6,9 MW)
Planning: 2005
Construction: 2006
Commissioning: Summer 2006
Operator:
Windpark Mastershausen
GmbH & Co. KG
Location:
Rhineland-Palatinate, Rhein-Hunsrück-Kreis, Kastellaun, Mastershausen