Kuhbett Windfarm (2018)


Production


kWh

CO2 -t CO2 avoided
Haushalte - German three-person model-households supplied

Kuhbett Windfarm

In the Kuhbett wind farm, four E-115 with a total output of 12.0 MW have been constructed on forested areas of the city of Bad Camberg and the Hessian Forestry. Private owners are not involved.

The area of the wind farm is one of the windiest areas in the entire region. However, in order to be able to correctly estimate the wind speeds at the location, DunoAir had therefore measured the conditions at 6 heights starting from August 2015 over a period of one year with a 140 m high measuring mast. The results then went directly into the planning.

In February 2016, DunoAir submitted the permit application according to the Federal Immission Control Act and received the notification at the end of December 2016. The wind farm was built mainly over the year 2017, so that the first wind turbines went into operation at the beginning of 2018.

The Kuhbett wind farm is connected to the public electricity grid via the Niederselters substation. Thus, about 7,300 average housholds can be supplied.

Show Energy Yield

Planning: 2015

Construction: 2017/18

Commissioning:

Early 2018

Turbines:

4 x E-115 (3,0 MW)

Location:

Hessen, Limburg-Weilburg County, City of Bad Camberg

Windstatistics
Little Feldberg

view statistics

Environmental balance

ESTIMATED YIELD28,3 MIO. KWH
CO2-SAVINGS17.500 TONS
SO2-SAVINGS16.400 TONS
ELECTRICITY FOR 7.300 3-PERSONS HOUSEHOLDS